Good preparation is everything
To start with, the company thoroughly took stock of the existing plant. Which electronic components, e.g. frequency converters, relays and switching modules, were installed, and which of those were compatible with the new control system? Everything was checked and replacements for any parts that were not compatible had to be ordered and delivered.
This thorough preparation period was crucial for precisely determining the scope of the new components and for preparing a reliable project schedule, as not only replacing the control software pre-installed on a computer was time consuming, but also the wiring of each individual new part. As the retrofit had to be done as part of the annual inspection work, Benninghoven/Gurtner had to plan everything around this date.