Two-track farm road and kerb-gutter profile in the space of one week
Wirtgen SP 33

Video of the SP 33 at work in Sieghartskirchen and in the Semmering Tunnel, Austria

From the plains of Lower Austria to the mountains of Styria

Two construction sites, numerous challenges and a machine that demonstrates its abilities as a real all-rounder.

After the team from Bickhardt Bau had been impressed by the new SP 33 at its market launch in January, the company decided to purchase the machine, which was then delivered to them at the Wirtgen factory in Windhagen. Shortly afterwards, the machine celebrated its first practical deployment on two projects that enabled it to demonstrate its enormous flexibility.

From left to right: Michael Auer, CEO Bickhardt Bau; Bernd Michel, Head of Equipment Technology Bickhardt Bau; Martin Datzert, Product Manager Wirtgen GmbH; Jürgen Seidel, Sales & Distribution Wirtgen Germany.

Tolles Produkt

With flexibility and precision on the road to success

On the first deployment in Austria, Bickhardt Bau worked together with the construction and civil engineering company, HABAU Hoch- und Tiefbaugesellschaft. It soon became clear just how different the applications for which they used the SP 33 could be. Within a week, two projects were in planning, on which the advantages of the versatile slipform paver soon became apparent. The first project on the agenda required the paving of a two-track road for agricultural use in Sieghartskirchen. After this, the machine was moved to the Semmering Tunnel to pave a kerb-gutter profile.

Thanks to the ability to quickly exchange the slipform moulds, the paving of the two radically different profiles was able to be completed in only a short space of time.

Two-track road for agricultural vehicle access in Sieghartskirchen

The SP 33 was first deployed in Sieghartskirchen, Lower Austria, where it was used to pave a two-track road for agricultural vehicle access. The project brief specified the paving of two tracks with a width of 1 metre and a gap of 1 metre between them. The verges on both sides and the gap between the concrete tracks were later filled with crushed stone or gravel. To produce the two tracks of the farm road, the machine was fitted with two slipform moulds, one on the left side of the paver and one on the right. The material was fed to the paver via the belt conveyor and evenly distributed to the two slipform moulds via a split chute.

Portrait photo of Michael Stefaner, member of the HABAU group management team

‘I have to say that the crew was over the moon from the first day on, and that no one has ever been so excited about a machine on its first day out.’

Michael Stefaner, Group Manager, Civil Engineering and Road Construction East, HABAU

As with all slipform paving projects, precise regulation of the height, cross slope and steering also played a decisive role in the construction of the two-track farm road and ensured production of the profiles in strict compliance with the project specifications. On the project site, the machine was controlled by means of a stringline – one of the many options offered by Wirtgen. An alternative would have been, for example, to use the stringline-free AutoPilot 2.0. The satellite-based control system automatically controls the height, steering and cross slope of the machine and replaces the conventional stringline with a virtual 3D model. The SP 33 also offers an option for height regulation and steering with the aid of a 3D system. Very useful alternatives that, in addition to high precision, offer several further advantages through the elimination of a physical stringline.

Kerb-gutter profiles in the Semmering Tunnel

A couple of days later, following the completion of the first project, the team from HABAU Hoch- und Tiefbaugesellschaft was already on its way to the next job, this time in the Semmering Tunnel in Styria.

The task that faced them there was the paving of kerb-gutter profiles on both sides of the tunnel. The particular challenge here was that the new kerb-gutter profile had to be paved on top of the existing kerb profile in the tunnel. This meant that the work had to be carried out with extreme precision in order to ensure the structural stability and durability of the profiles. Following the completion of this work, a two-layer concrete track was paved between the two profiles with an SP 1500.

Portrait photo of Bernd Haberl, Foreman at HABAU Hoch- und Tiefbaugesellschaft

‘We got the job that would usually take us two or three days over and done with in just one day.’

Bernd Haberl, Foreman at HABAU Hoch- und Tiefbaugesellschaft, underlining the flexibility of the slipform paver.

As the tunnel is an important north-south traffic route, the construction project had to be completed as quickly as possible. Since only eight bolts need to be loosened when exchanging moulds on the SP 33, the team was able to save a lot of valuable time.

Two construction sites, numerous challenges and a machine that demonstrates its abilities as a real all-rounder. The projects in Austria once again demonstrated the importance of flexibility and adaptability on the construction site and the contribution that the SP 33 can make in this respect.

You can find more details and further information on our product pages.

Press/media kit

Click here to download a ZIP file containing the press release in the available languages in Microsoft Word format and the images in 300 dpi resolution.

Download