Base layer rehabilitation with a CR series machine
The cost-efficient alternative to traditional road rehabilitation methods can save time and money.
In Markt Indersdorf, around 50 km north of Munich, cutting-edge technology meets resource-efficient construction processes. Here, paving contractor SSP Seizmeir Straßen- und Pflasterbau GmbH produced a new base layer in just 3 Tagen with a CR series cold recycler – and not only cut the construction time by 6 to 8 weeks, but also significantly reduced the burden on local taxpayers.
Germany’s road systems are plagued by an enormous backlog of planned or pending rehabilitation projects – especially in the case of communal infrastructure. The main causes of this are high traffic density, adverse weather conditions and long construction times. Traditional road rehabilitation methods are often pushed to the limit when it comes to cost-efficient project fulfilment. Material and transportation costs are high, construction times are long, and the usage of resources is often also correspondingly high.
With in situ cold recycling, Wirtgen offers a pioneering alternative that is cost-efficient, resource-friendly and quickly achievable – an ideal solution for regional, local and communal roads.
A cold recycling train, comprising a W 240 CRi, a Streumaster SW 16 MC, a John Deere JD 672 GP Grader, two Wirtgen milling machines W 150 CFi and W 130 Fi, a Vögele Super 2100-5i paver, and several Hamm rollers.
Contractor SSP Seizmeir Straßen- und Pflasterbau GmbH from Scheyern relied on a CR series cold recycler for the rehabilitation of the ST 2045 with foamed bitumen technology. Here, hot bitumen is foamed by the addition of precise amounts of air and water and added to the mixing process together with small quantities of a pre-spread cement binder. As a rule, the surface layers, made up of asphalt or granular material, are taken up and mixed with binding agents in a single pass. In the mixing chamber of the CR, the foamed bitumen forms fine micro-bonds within the material. These bonds are decisive for ensuring the long-term elasticity of the BSM (Bitumen Stabilized Material) used as a new base layer.
The material is transferred directly from the CR to the material hopper of the Vögele paver and laid down as the train advances. Here in Markt Indersdorf, with an impressive production rate of 360 tonnes per hour. No transportation of material away from the site, no intermediate stockpiling, and, depending on the construction site, no new base layer material required – simply uncomplicated, fast and resource-friendly.
The materials were tested in the construction materials laboratory before the start of the project to find the ideal recipe for the new base layer. In the course of this, it was determined that the existing 50 – 80 mm asphalt surface layer would be insufficient for the desired end result.
In view of this, additional reclaimed asphalt pavement (RAP) from nearby construction sites was mixed in during the cold recycling process to produce the desired 160 mm BSM base layer.The 100 mm layer of RAP augments the existing asphalt surface layer and, together with the cement binder and foamed bitumen, is a further ingredient of the mix for the new base layer of the road.
The result: a homogeneous, bitumen stabilised base layer – almost entirely without the addition of new construction materials.
The entire construction project was realised exclusively with cutting-edge Wirtgen Group technology.
Preparation:
Cold recycling:
Surface layer paving:
‘This saves us a having to move truckloads of material. It’s a big advantage that we can turn the material into a new and better base layer right here on the site.”
Stefan Hausmann, Senior Site Engineer at SSP Seizmeir Strassen- und Pflasterbau GmbH
The existing base layer consisted of the round gravel typically used in this region – a material that was assessed as unsuitable for inclusion in the cold recycling process. The CR and the milling machines milled down precisely to the upper boundary of the gravel layer. This meant that the road bed would remain untouched and that the new 160 mm base layer would actually be augmented. The now thicker layer structure thus increases the load-bearing capacity of the road. In the final step, the BSM base layer was paved over with an only 40 mm thick surface layer of new asphalt. ‘We are now rehabilitating the road with the cold recycling method with a complete recycling train of Wirtgen Group machines,’ explains Stefan Hausmann. ‘We are paving a new and stronger base layer with additional milled material from another construction site. The big advantage: it’s a lot faster than complete removal.’
‘We are recycling here in-situ and paving a better base layer with greater long-term durability than what the road has had up to now.’
Stefan Hausmann, Senior Site Engineer at SSP Seizmeir Strassen- und Pflasterbau GmbH
The entire cold recycling train works as a rolling construction site along the road, which was able to be used in front of it and behind it, even by heavy agricultural machinery. The access road to a farm, for example, was only closed off for around an hour. An advantage that cannot be overlooked in many regions.
More details and further information can be found on our product pages.