Flat out for this commuter route: to enable 3.6 km of motorway to be rehabilitated in just 55 hours, two spray pavers worked on the surface course simultaneously in each direction of travel – each of them supported by a material feeder.
“Hot to hot” paving with two SUPER 1800-3i SprayJet pavers: VÖGELE spray technology has proved itself over many years in a variety of projects all over the world – including the high-speed motorway job site near Duisburg.
More flexibility: its pivoting conveyor means that the VÖGELE MT 3000-2i Offset material feeder can supply two pavers with mix. This allows the two paver operators to give their full attention to the paving process.
Innovative technology, clean job site: SprayJet technology from VÖGELE dispenses with the separate operation of spraying with bitumen emulsion in advance.